Wi-Fi Upgrades in Academic and Research Areas (Project UIT16919)

Overall Project Status: In Progress

Project Goals & Objectives

  • Meet or exceed our SLA of minimum 5Mbps in all academic and research areas
  • Upgrade Wi-Fi access points and cover rooms at capacity in all academic and research areas

Scope of Work

  • Buildings: Science and Research 1, Science and Research 2, Fleming, Health and Biomedical Sciences, Science and Teaching Lab, SERC, SEC, PGH, and Garrison (CASA)
  • Upgrade of 170 existing access points to 802.11n, move them below the ceiling to meet current design standards, and install 165 additional access points

Major Milestones

ACTIVITY START END NOTES
SR1 550 6/1/16 6/29/16 SR1 will be substantially completed on Wednesday 6/29
Fleming 564 6/1/16 6/30/16 Fleming will be substantially completed on Thursday 6/30
SR2 551 6/4/16 6/30/16 SR2 will be substantially completed on Thursday 6/30
Garrison 532 6/4/16 6/29/16 Garrison will be substantially completed on Wednesday 6/29
HSC 593 6/5/16 6/29/16 HSC will be substantially completed on Wednesday 6/29
PGH 547 6/6/16 7/1/16 PGH will be substantially completed on Friday 6/31
SEC 545 6/20/16 7/1/16 SEC will be substantially completed on Friday 7/01.
SERC 545 6/7/16 7/12/16 SERC will be substantially completed on Friday 7/12
STL 6/8/16 7/12/16 STL will be substantially completed on Wednesday 7/12 i
All Buildings 7/13/16 8/9/16 QA and configurations in all buildings
Project End 8/10/16 Project will be substantially completed on Wednesday 8/10